Thursday, 27 August 2015

Friday 28th August 2015.

This week saw us commence work on the redevelopment of the 8th tee complex.

This hole will be shortened overall and an elevated rear tee constructed. The main cyclic tee will be built around the 120 metre distance and the ladies tee moved forward with a secondary ladies tee developed on the right hand side of the hole that can be used when hole locations are on the left side of the green.

The majority of the earthworks are now complete and irrigation to service this area will be installed next week. Turfing of the teeing areas should be completed within the next fortnight.

The rear area will be planted out with flowering shrubs and grass trees to enhance this area.

harvesting turf off the old tee.
Earthworks commence.
Things start to take shape.