Monday 24th December 2012
Much of the reconstruction work for the 8th green is now complete with the final turf going down last Friday 21st December and this is all now in the grow-in stage.
The turf on the putting surface itself is showing good growth and regular mowing is now underway. This surface will be topdressed for the first time very soon and this will help firm it up for play.
Some extra grass will be planted on the extremities of the construction site to blend turf to surrounding areas and this should develop fairly rapidly.
A light scarification of the older fairway turf on the approach soon, will encourage good recovery of this turf that had been stored for a couple of weeks and looks somewhat scarred.
Once turf on the surround has established itself well enough, the bunkers will receive their final shaping and have bunker sand placed in them.
All things going well, the anticipated opening of this hole should be mid February.
Sunday 23 December 2012
Thursday 13 December 2012
Friday 14th December
We have had a very productive week this week with the relaying of the 8th green and the commencement of turf laying on the approach and surround.
Next week the remaining turf on the surrounds and around bunkers will be completed and a irrigation station will be installed to water this surround.
All turfing should be completed by the end of next week and grow-in underway over the Xmas break.
The finished turfed green.
Approach to the green has been re-turfed with just the turfing of surround and bunkers required.
We have had a very productive week this week with the relaying of the 8th green and the commencement of turf laying on the approach and surround.
Next week the remaining turf on the surrounds and around bunkers will be completed and a irrigation station will be installed to water this surround.
All turfing should be completed by the end of next week and grow-in underway over the Xmas break.
The finished turfed green.
Approach to the green has been re-turfed with just the turfing of surround and bunkers required.
Tuesday 11 December 2012
Wednesday 12th December.
Work has progressed well on the reconstruction of the 8th green complex. Harvested turf from fairway has been relayed and the irrigation stations to serve the approach area and green have been installed.
Final levelling on the green was completed earlier in the week and the laying of the putting surface started on Tuesday. The laying of the green will be completed by Wednesday.
Thursday will see the installation of another irrigation station around the back and sides of the complex to service the surround areas and we shall also commence the returfing of the remainder of the approach and surrounds. As this is quite a large area, I am expecting that this will go well into the middle of next week.
Work has progressed well on the reconstruction of the 8th green complex. Harvested turf from fairway has been relayed and the irrigation stations to serve the approach area and green have been installed.
Final levelling on the green was completed earlier in the week and the laying of the putting surface started on Tuesday. The laying of the green will be completed by Wednesday.
Thursday will see the installation of another irrigation station around the back and sides of the complex to service the surround areas and we shall also commence the returfing of the remainder of the approach and surrounds. As this is quite a large area, I am expecting that this will go well into the middle of next week.
The relaying of turf on the approach and operation of new irrigation station.
The laying of turf on the putting surface using turf grown on our bentgrass nursery for the past 9 months.
Wednesday 5 December 2012
Thursday 6th December.
Work is progressing well with the reconstruction of the 8th green complex. Final shaping of the green and bunkering as well as the approach area is almost complete. A ring main to service the green and an irrigation station to service the approach have been completed and work will commence very soon on the re-grassing of the approach area. Turfing of the green will most likely start around next Tuesday 12th December.
Work is progressing well with the reconstruction of the 8th green complex. Final shaping of the green and bunkering as well as the approach area is almost complete. A ring main to service the green and an irrigation station to service the approach have been completed and work will commence very soon on the re-grassing of the approach area. Turfing of the green will most likely start around next Tuesday 12th December.
Shaped greenside bunker.
Installation of irrigation on approach area.
Subscribe to:
Posts (Atom)